In 2019, club members and the Board approved a state-of-the-art, four-court indoor tennis centre. Although COVID-19 has slowed the construction start date, the project is still moving forward. We know how sought after indoor court time is, and our careful planning, designing, and financial management will bring this exciting new development to life! 

The Derrick Club has a special offering for those interested in playing tennis in our future facility. Please fill in this form below so we can contact you with more details.

()-

Construction Updates


April 28, 2021


4 Week Look Ahead

April 23
delivery and setup of temporary fencing; on site private utility locates.

April 26–30
remove light standards; site survey; Alberta One Call locates.

1st week of May
remove tennis court surfacing and excavate; remove south parking lot surfacing; south portion of water line install.

2nd week of May
rough grading both parking lots; water service room construction; water line install within curling.

3rd week of May
electrical trenching, light standard piling; water service room construction; water line install within curling.

4th week of May
curbs and sidewalks; water service room construction; water line install within curling.


March 15, 2021


We are excited to bring you our first update on the status of the indoor tennis facility. The Board approved the restart of the indoor tennis courts on January 26, 2021. An Indoor Tennis Construction Committee has been developed to assist in the Delivery of this Capital Construction Project consisting of our General Manager Jim Hope, 3 Board Members, and 2 Members at Large with Construction Backgrounds.
 
Following a competitive Request For Proposal process to select a General Contractor, the Committee selected Carlson Construction and have awarded a Fixed-Price contract. The Carlson Team has extensive experience working on similar projects at other Private Clubs and successfully completed the Derrick Badminton Facility in 2014. They understand the club and have always provided a great result with a keen eye on the budget and schedule.
 
Here is a high level look at our schedule:
 
Feb
Contract signed
Financing secured
 
March/April
Sub trades secured
Metal building ordered
Existing outdoor tennis court fencing and lighting removal
 
May
Existing tennis courts converted to parking
New south parking by skating rink constructed
 
July
New parking open
Building construction commences (piling, tennis court surfacing, structural steel)
 
Feb/Mar 2022
New indoor tennis facility target opening

Redefining Tennis in Edmonton

The playing surface for the new tennis courts will be plexicushion. This is a very popular surface favoured by a number of private clubs because it is considered less jarring on players body and less stressful on joints. Derrick Club members will be able to challenge their friends and family on the same playing surface the pros use at the Australian Open.

A top of the line indirect LED lighting system will enhance the players’ experience throughout the facility.

More for Members

The Derrick Club is expanding the athletics program with an all-new indoor tennis centre! The centre will have four indoor tennis courts with plexicushion surface and a variety of programs for all levels. The design and budget are approved and the centre is ready for development.

Athletic members have full access to the courts and online booking will be available.


Contact Lindsey Pelechytik at lp@derrickclub.com or 780.437.8385 for more information or a tour.